Commissioning & Test
As part of the Project Management procedure, a bespoke test procedure will be written and provided as part of the handover documentation to the client.
The procedure may encompass a number of tests, below is a sample of requirements:-
- SPL performance levels for each zone or defined area
- STI (intelligibillity) performance figures for each zone or defined area
- Loudspeaker circuit test sheets, Impedance, Earth continuity, EOL value etc.
- Fire or Emergency Microphone operation tests
- Paging microphone tests
- Fire Alarm interface tests
- Message broadcast equipment (digital mesage stores)
- Redundancy / Network resilience testing
- PC operation
- Stagebox and multicore testing
- System DSP setting verification and backup file save.
Whilst this list is not aplicable to all projects, it provides a basis to work with and then develop a site specific full test, commission documents. These documents should then be made part of the final handover documents.